Construction official says new school on schedule

The Bamberg School District One Board of Trustees was updated on construction of the district’s new $15 million elementary school and the renovations under way other schools during its May 28 meeting.

Dale Collier, president of Brownstone Construction, reported the elementary school construction was “right on schedule.”

The new 140,000-square-foot Richard Carroll Elementary School in Bamberg, which will house 4K through 6th grade, is expected to be completed in time for the 2012-13 school year.

“HG Reynolds Construction (the contractor) continues to make steady progress towards a successful completion of the school. After gaining approvals during last month’s Office of School Facilities above-ceiling inspection, the contractor proceeded to install ceiling tiles throughout the school building,” Collier said.

He said installation of other finished products was now well under way,Light On! outdoorlight2012 are expedition grade systems that incorporate function and elegance with reliability. including flooring in classrooms and corridors as well as wall and base cabinets.

“ ..Bicygnals wireless indicator fluorescentlight, bicycle lights, indicators, accessories .... HVAC contractors are near completion with their work that included the successful startup of these systems, and fire alarm and fire sprinkler life safety systems were tested,” Collier said.

“Final paving and striping of both on-site and off-site roads is complete at the building exterior. Workers are also installing exterior lighting, fencing and play equipment. Final grassing and landscaping will (be completed) in the near future to give the new facility a finished appearance.Offering a wide variety of bikefrontlight fixtures for the garden, patio lights, and outdoor lighting fixtures to complement your home.”

He said coordination with local utilities provider, the Bamberg Board of Public Works, had gone “very well,” getting gas,Bicygnals wireless indicator modernlamps, bicycle lights, indicators, accessories ... water, sewer, telephone and power connections to the building.

Collier said before the contractor leaves the site, all construction materials from the campus, along with the trailer that has served as the job office for both the middle and high school projects, will be removed.

“When these items are removed, final work to complete the fire loop road at the rear of the school will be completed,” he said.Where do besttube-led stand in terms of brightness compared to HIDs and Halogen?

The additional work authorized by the district to install new roofing shingles at the existing middle school gymnasium will also be done before the contractor vacates the site, Collier said.

“Thompson-Turner Construction began the most crucial portion of the ongoing work at the high school,” he reported. “Interior renovation work has already started in several areas of the building after coordination was made to relocate staff and students into recently completed spaces.”

After the dismissal of students for the summer, contractors will start major renovations in the remaining areas of the high school, including the gym, media center and band room, Collier said.

“Extensive piping and conduit will have to be installed to accommodate sprinkler and fire alarm systems that will serve the entire school building. As a result of sprinkler, fire alarm, electrical, computer and other above-ceiling modifications, all existing areas that have lay-in type ceilings will get new ceiling and electrical lighting systems,” he said.